Dismantle, Refurbish, Relocate 21 STPD Gaseous Nitrogen Plant; South-central USA |
UIG received a request from a
regional U.S. industrial gas company for a small cryogenic nitrogen plant to use
as an onsite supply system for a new customer.
The required schedule for plant installation was tight, as UIG's customer was
required to begin delivering
gas to their onsite customer in a few months.
UIG identified a suitable used plant, but it was still in service in the Midwest and had to continue operating at its existing site for several more weeks. UIG mobilized its relocation crew in Illinois, in advance of plant shutdown, to ensure that dismantlement work could begin as soon as the nitrogen generator had been idled. |
![]() |
![]() |
![]() |
N2 Plant being Re-installed in Texas |
Closer View during Construction |
Overview near Completion |
UIG provided engineering, equipment supply, dismantlement, transportation, erection, commissioning and start up services for the relocated plant. Plant components were replaced or refurbished as necessary. The plant was ready for installation in Texas nine weeks after starting the relocation project - as promised in the UIG proposal and guaranteed in the plant purchase agreement. |
![]() |
![]() |
![]() |